(1) The damaged part of the coating film should be repaired in time during the installation process. Due to the damage caused by welding, calibration and other reasons , it is necessary to re-derust the steel plate during painting, and then apply the corresponding supporting paint.
(2) When the free edge of the steel plate structure appears, it should be rounded, and the welding slag and welding tumor on the surface of the steel plate on both sides of the weld bead and weld should be removed, and the rust removal quality should meet the requirements of ()"*% level. 1. The weld seam is first painted with a primer, and then the corresponding supporting paint is painted.
(3) Large-scale outfitting such as masts, columns, chimneys, etc. shall be primed, intermediate coated, installed on board, and then painted in the same way as other outfitting.
(4) Before the delivery of the ship, paint the final deck paint and hull paint, and finish the painting at one time.
(5) The paint of the liquid tank should be put into use and loaded with articles after the paint is completely cured and dried two weeks after the paint is completed .
(6) The safety protection work during painting shall be carried out in accordance with the relevant contents of Chapter VII.
(7) It is forbidden to paint on sacrificial anodes, insoluble auxiliary anodes, reference electrodes, receiver and transmitter threads of depth sounders, signs, rubber seals, valves, steel cables, movable friction surfaces, propellers, etc. painted. When spraying or applying by other methods, cover with adhesive tape, remove .