How to install the special water purifier for MOLSUN-105A Conditioning machine?

1. Working conditions

Operating Voltage

220V±10%/50Hz, with reliable grounding

power

100W  

raw water temperature

5-40℃

tap water pressure

0.15-0.25Mpa (If it is higher than 0.25 Mpa, the customer needs to take decompression measures, otherwise it is easy to cause overpressure damage and water leakage; if it is lower than 0.15 Mpa, the equipment will alarm and stop, and a booster pump needs to be added)

working environment

The installation site should try to ensure a ventilated and dry environment, and the temperature should be between 5-30°C; especially in northern areas, prevent the instrument from freezing in winter. The freezing of water in the instrument will cause the instrument to be effectively damaged; do not place the equipment in a place with high acidity. big environment 

2. Installation diagram:

How to install MOLSUN-105A special water purifier for aging machine?  Picture 1

3. Installation steps:

3.1 Please disconnect the water source and power supply;

3.2 Please connect the three-way direct head and the faucet switch in the accessories to the tap water switch (use raw tape to seal it without leaking), and then use 2 points of white PE pipe to connect the raw water outlet at the rear of the machine to the outlet of the faucet switch.

3.3 Cut the appropriate length of a white PE pipe into the waste water outlet of the machine (one is a quick socket), and insert the other end into the sewer or floor drain (fix the pipe after it is inserted to prevent the pipe from popping out of the sewer) for drainage (note: this drainage The pipe must not be bent or blocked).

3.4 Cut the white PE tube to an appropriate length of 3 minutes and connect it to the QSUN machine.

3.5 Insert the power cord plug of the machine into a 220V socket that meets the installation standard.

3.6 After the above pipe connections are completed, first turn on the tap water switch, and then turn on the power switch on the back of the machine. Then press the start button on the front of the machine, and the machine starts to work (if the tap water is not turned on or the tap water pressure is too low, the machine will alarm). At this time, the machine will automatically flush for 3 minutes (the RO flushing light is on). After 3 minutes, it will automatically switch to the water production state, the water production indicator light will be on, and the resistance meter will display the current water quality (generally 10 MΩ.CM) and the water supply pressure value (Kg).

3.7 Check whether there is water leakage at each pipe connection. The installation is complete.

3.8 In the case of continuous water and electricity, this machine is fully automatic control, automatic water production, standby, and delivery. The normal maintenance is to replace the consumables regularly (see attached consumables replacement table).